This project involved the relocation of Gibsons MMA to a new facility just a few doors down. Long-time partners of Saltire Contracting, Lance, Julia, and Lance Jr. approached us to assist with the build-out of the new space.
Due to tight timelines, we worked closely with Lance to finalize the design and scope of work without issuing a formal tender. The build-out was completed in just 11 working days.
The scope included reframing and insulating walls and ceilings, installing a full electrical system with 64 pot lights, constructing two bathrooms, applying epoxy flooring, painting, and relocating mats, gym equipment, and the cage. Despite the project's demands, we ensured its successful and timely completion.